--- PAGE 1 --- LEARN MORE ESKAYIBA.TAHLTAN.ORG #2 – COMMUNITY INFORMATION SESSION Date: September 7, 2022 Location: Iskut TCG Participation or Lead: No Presentation: No Session Notes: Skeena hosted a hybrid community engagement in Iskut with Skeena representatives joining in person and online. The presentation provided an update on the Eskay Creek Revitalization Project’s EA and the Section 7 Agreement. Community members raised questions about how Skeena would support education and training opportunities and how the EA process is considering social impacts to Tahltan communities. #3 – COMMUNITY INFORMATION SESSION Date: September 7, 2022 Location: Telegraph Creek TCG Participation or Lead: No Presentation: No Session Notes: Skeena hosted a Tahltan community information session at the Telegraph Creek Recreation Centre on September 7, 2022, providing team member introductions, status update on the Eskay Creek Revitalization Project along with a EA process updates. Community members attended and raised questions about Skeena’s plans for upcoming engagements in Tahltan Territory and about contracting and employment opportunities at the Project site. #1 – COMMUNITY INFORMATION SESSION Date: September 1, 2022 Location: Dease Lake TCG Participation or Lead: No Presentation: No Session Notes: Skeena hosted a Tahltan community information session held in Dease Lake on September 1, 2022. Skeena provided team member introductions, a status update on the Eskay Creek Revitalization Project along with the Environmental Assessment (EA) process updates. ENGAGEMENT SESSIONS FOR ESKAY CREEK REVITALIZATION PROJECT AND/OR IBA --- PAGE 2 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 2 #6 – COMMUNITY INFORMATION SESSION Date: October 27, 2022 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Yes Session Notes: TCG presented an overview of the Section 7 Consent Based Decision-Making Agreements and Tahltan Risk Assessment Process. #7 – COMMUNITY INFORMATION SESSION Date: January 31, 2023 Location: Virtual TCG Participation or Lead: Yes Presentation: 2023 01 31_VIS Skeena_Eskay Creek Revitalization.pdf Session Notes: The B.C. Environmental Assessment Office (EAO) held a Public Virtual Information Session with Skeena and TCG on January 31, 2023 to provide an update on the Project’s environmental assessment process. #8 – COMMUNITY INFORMATION SESSION Date: February 2, 2023 Location: Virtual TCG Participation or Lead: Yes Presentation: 2024 01 31_VIS Skeena_Eskay Creek Revitalization.pdf Session Notes: The B.C. EAO hosted a Virtual Information Session for the Project. There were presentations from the EAO, TCG and Skeena Resources on the Project, including EA process and the Process Planning Documents that were currently open for Tahltan member and public comment. #5 – COMMUNITY INFORMATION SESSION Date: October 26, 2022 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: Yes Session Notes: TCG presented an overview of the Section 7 Consent Based Decision-Making Agreements and Tahltan Risk Assessment Process. #4 – COMMUNITY INFORMATION SESSION Date: October 25, 2022 Location: Iskut TCG Participation or Lead: Yes Presentation: Yes Session Notes: Tahltan Central Government (TCG) presented an overview of the Section 7 Consent Based Decision- Making Agreements and Tahltan Risk Assessment Process. --- PAGE 3 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 3 #9 – COMMUNITY INFORMATION SESSION Date: February 15, 2023 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: Process Planning Session Notes: TCG held community engagement sessions with Tahltan membership and the B.C. EAO, with participation by Skeena to discuss the Tahltan Section 4 Application Information Requirements, Tahltan Assessment Areas and seek input and direction regarding Tahltan Values to be included as part of the Environmental Assessment. #10 – COMMUNITY INFORMATION SESSION Date: February 16, 2023 Location: Iskut TCG Participation or Lead: Yes Presentation: Process Planning Session Notes: TCG held community engagement sessions with Tahltan membership and the B.C. EAO, with participation by Skeena to discuss the Tahltan Section 4 Application Information Requirements, Tahltan Assessment Areas and seek input and direction regarding Tahltan Values to be included as part of the Environmental Assessment. #1 1 – COMMUNITY INFORMATION SESSION Date: February 17, 2023 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Process Planning Session Notes: TCG held community engagement sessions with Tahltan membership and the B.C. EAO, with participation by Skeena to discuss the Tahltan Section 4 Application Information Requirements, Tahltan Assessment Areas and seek input and direction regarding Tahltan Values to be included as part of the Environmental Assessment. #12 – COMMUNITY INFORMATION SESSION Date: April 11, 2023 Location: Dease Lake TCG Participation or Lead: Yes Presentation: 2023 04 04 Tahltan Community Visits Round 7.pdf Session Notes: Skeena and TCG hosted a community information session in Dease Lake. Skeena presented the planned activities for the Eskay Creek Project including the development of a warehouse pad, assay laboratory and continued site investigations for collecting baseline data and project environmental assessment information. Community members raised questions about training opportunities and the use of social baseline data in the EA Process. --- PAGE 4 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 4 #13 – COMMUNITY INFORMATION SESSION Date: April 13, 2023 Location: Iskut TCG Participation or Lead: Yes Presentation: 2023 04 04 Tahltan Community Visits Round 7.pdf Session Notes: Skeena hosted an open community information session in the community of Iskut. There were representatives from the TCG Lands Department present at the meeting. Skeena presented an update of planned activities on the Eskay Creek Project site for the summer of 2023, including work on the warehouse pad, construction of an assay lab, and continued exploration and characterization work at the site. The presentation also included an update on the environmental assessment process. #14 – VIRTUAL INFORMATION PACKAGE Date: June 19, 2023 Location: All Tahltan Membership TCG Participation or Lead: Yes Presentation: Information Package Emailed to Tahltan Membership “What We Heard” – With options for Comments to Lands Director Email. Session Notes: N/A #15 – COMMUNITY INFORMATION SESSION Date: June 20, 2023 Location: Dease Lake TCG Participation or Lead: Yes Session Notes: TCG and Skeena held a Community Open House in Dease Lake with Grade 10-12 students from the Dease Lake School; 18 people attended. A brief presentation was given by Skeena and TCG introducing the Project and the EA process. Input and feedback received related to clarity on quiet enjoyment of land, the importance of the presence of animals at the Project site after closure, concern about decreasing moose populations in Tahltan Territory and how it affects ability for Tahltan members to hunt for food; and interest in future engagements. #16 – ELDERS LUNCHEON Date: June 20, 2023 Location: Dease Lake TCG Participation or Lead: Yes Session Notes: TCG and Skeena held a Community Open House in Dease Lake with the community elders; nine participants attended. Skeena and TCG presented on the Project as well as the EA. Input and discussion focused on vegetation species used for medicinal purposes, water quality, human and wildlife health, fish and fish habitat, cumulative impacts, mine closure and procurement. --- PAGE 5 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 5 #17 – ELDERS LUNCHEON Date: June 22, 2023 Location: Iskut TCG Participation or Lead: Yes Session Notes: TCG and Skeena held a Community Open House in Iskut for community elders. Skeena and TCG representatives presented on the Project and EA. Input and discussion focused on vegetation species used for medicinal purposes, water quality, human and wildlife health, fish and fish habitat, cumulative impacts, mine closure and procurement. #18 – COMMUNITY INFORMATION SESSION Date: June 22, 2023 Location: Iskut TCG Participation or Lead: Yes Session Notes: TCG and Skeena held a Community Open House in Iskut for the Iskut community. The Community Open House included poster stations on various topics on the Project. Input and feedback received related to what the Project site will look like after closure; the importance of the site being returned to pre-mining state; cumulative effects in Tahltan Territory on road safety, social issues and if there are fish present at the Project site. #19 – COMMUNITY INFORMATION SESSION Date: June 23, 2023 Location: Telegraph Creek TCG Participation or Lead: Yes Session Notes: TCG and Skeena held a Community Open House in Telegraph Creek for the community to discuss topics on the Project. Input and feedback received related to equipment (i.e., helicopter), or people disturbing quiet and pure experience on the land; closure; how drought is considered in the design for the Tom MacKay Storage Facility; reduction in frogs near Bob Quinn; water quality discharge; and interest in engagement materials. #20 – ELDERS LUNCHEON Date: June 23, 2023 Location: Telegraph Creek TCG Participation or Lead: Yes Session Notes: TCG and Skeena held a Community Open House in Telegraph Creek with Tahltan Elders. Input and feedback received related to the stability of the Tom MacKay Storage Facility; how is TCG considering the impacts of multiple mines in Tahltan Territory; requests for an increase in community infrastructure in Telegraph Creek; potential impact to salmon in the Unuk River; how working at mining camps is affecting Tahltan member’s ability to learn on the land skills and their ability to participate in the Tahltan Way of Life; and request that younger elders be invited to these engagements. #21 – AGA ELDERS PRESENTATION Date: July 1, 2023 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Elders Presentation Session Notes: TCG Lands Department provided an update at the Elders Council on status of Eskay Creek Project. --- PAGE 6 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 6 #22 – AGA MEMBERSHIP PRESENTATION Date: July 2, 2023 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Full Membership Presentation & TCG Lands Department Booth Session Notes: The TCG Lands Department provided a formal update to membership on all major projects during the 2023 AGA. Eskay Creek and the status of the Tahltan Risk Assessment was presented during the Lands Director’s formal AGA membership update. Additionally the Lands Department Staff were available over a three day period to answer questions, provide information and discuss with membership aspects of the Eskay Creek Project. #23 – COMMUNITY INFORMATION SESSION Date: September 21, 2023 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: 2023 09 09 Tahltan Community Visits Round 8_v3.pdf Session Notes: Skeena, Tahltan ERM Environmental Management (TEEM), and TCG hosted a Tahltan community information presentation in Telegraph Creek for residents to provide updates on the status of the Environmental Assessment, seek additional input and information during the Application Development Phase and report out to membership. Topics of interest included production timeline, tailings pond, Tahltan workforce, open pit, wildlife, Assay lab testing, drainage, reconciliation actions, youth support, and community training opportunities. #24 – COMMUNITY INFORMATION SESSION Date: September 28, 2023 Location: Dease Lake TCG Participation or Lead: Yes Presentation: 2023 09 09 Tahltan Community Visits Round 8_v3.pdf Session Notes: Skeena, Tahltan ERM Environmental Management (TEEM), and TCG hosted a Tahltan community information presentation in Dease Lake for residents to provide updates on the status of the Environmental Assessment, seek additional input and information during the Application Development Phase and report out to membership. Topics discussed included the open pit, Skeena representatives, mental health, communication poster format, and Tahltan benefits. #25 – COMMUNITY INFORMATION SESSION Date: October 26, 2023 Location: Iskut TCG Participation or Lead: Yes Presentation: 2023 09 09 Tahltan Community Visits Round 8_v3.pdf Session Notes: Skeena, Tahltan ERM Environmental Management (TEEM), and TCG hosted a Tahltan community information presentation in Iskut for residents to provide updates on the status of the Environmental Assessment, seek additional input and information during the Application Development Phase and report out to membership. Topics of interest included production timeline, tailings pond, Tahltan workforce, open pit, wildlife, Assay lab testing, drainage, reconciliation actions, youth support, and community training opportunities. --- PAGE 7 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 7 #26 – TAHLTAN OPEN HOUSE Date: November 21, 2023 Location: Whitehorse TCG Participation or Lead: No Presentation: No Session Notes: Skeena hosted a Tahltan Open House in Whitehorse to bring community members together. The session was hosted by Nalaine Morin, and included words from Jeanie McLean. There was no formal presentation. #27 – COMMUNITY INFORMATION SESSION Date: January 17, 2024 Location: Prince George TCG Participation or Lead: Yes Presentation: No Session Notes: Skeena hosted a community engagement session with TCG participation to discuss the Project and EA Process. Topics of discussion included mining activities at Albino Lake, business opportunities, training programs/employment for Tahltan citizens, negations for an Impacts Benefit Agreement (IBA), youth, and environmental management/closure and reclamation plans for the Project. #28 – COMMUNITY INFORMATION SESSION Date: March 22, 2024 Location: Whitehorse TCG Participation or Lead: Yes Presentation: Membership Open House with Information Packages and Project Videos Session Notes: TCG hosted a joint open house where Skeena was invited to attend to present progress on the Project. Topic discussed included vegetation, wildlife, water, heritage, fish and aquatics, an overview on the Valued Components, the Project and the closure and reclamation process. Project handouts were also provided to attendees, in addition to project virtual information videos. Key themes highlighted included the importance of water and wildlife to the Tahltan and interest in business and employment opportunities. #29 – COMMUNITY INFORMATION SESSION Date: June 11, 2024 Location: Iskut TCG Participation or Lead: Yes Presentation: 20240608-June Tahltan Community Engagement.pdf Session Notes: Skeena and TCG held a joint community open house in Iskut. Comments from community were on various topics including fire management practices, wildlife interactions, critical minerals, mine road access, quiet enjoyment of the land and connection to self. This continued advancing discussion on the development of the Project’s Environmental Assessment Certificate (EAC) Application. --- PAGE 8 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 8 #30 – COMMUNITY INFORMATION SESSION Date: June 12, 2024 Location: Dease Lake TCG Participation or Lead: Yes Presentation: 20240608-June Tahltan Community Engagement.pdf Session Notes: Skeena and TCG held a joint community open house in Dease Lake, BC. Comments from community included wildlife surrounding Eskay Creek, Quiet Enjoyment of the Lands, EAC application engagement and community investment. This continued advancing discussion on the development of the Project’s EAC Application. #31 – COMMUNITY INFORMATION SESSION Date: June 13, 2024 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: 20240608-June Tahltan Community Engagement.pdf Session Notes: Skeena and TCG held a joint community open house in Telegraph Creek. Comments from community included tailings capacity, fish, and industry’s support for local needs and economy. This continued advancing discussion on the development of the Project’s EAC Application. #33 – COMMUNITY INFORMATION SESSION Date: October 8, 2024 Location: Iskut TCG Participation or Lead: Yes Presentation: Application Review Presentation Session Notes: TCG conducted a Tahltan-focused engagement open house in Iskut, where Skeena was invited to participate. The presentations provided information on the Project’s EAC Application, the identified project effects, and impacts and proposed mitigations and management approaches. #32 – ESKAY CREEK PROJECT SITE TOUR Date: July 2, 2024 Location: Eskay Creek Project Site TCG Participation or Lead: No Presentation: 20240608-June Tahltan Community Engagement Session Notes: Skeena provided a site tour to Tahltan Elders on July 2, 2024. The presentation includes an overview of the Project, EA and Quiet Enjoyment of Land. --- PAGE 9 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 9 #35 – TAHLTAN OPEN HOUSE Date: October 9, 2024 Location: Terrace TCG Participation or Lead: No Presentation: No Session Notes: Skeena hosted a Tahltan Open House in Terrace to bring community members together. The session was hosted by Tamlyn Botel and Jodi Payne. There was no formal presentation. #34 – COMMUNITY INFORMATION SESSION Date: October 9, 2024 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Application Review Presentation Session Notes: TCG conducted a Tahltan-focused engagement open house in Dease Lake, where Skeena was invited to participate. The presentations provided information on the Project’s EAC Application, the identified project effects, and impacts and proposed mitigations and management approaches. #36 – COMMUNITY INFORMATION SESSION Date: October 10, 2024 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: Application Review Presentation Session Notes: TCG conducted a Tahltan-focused engagement open house in Telegraph Creek, where Skeena was invited to participate. The presentations provided information on the Project’s EAC Application, the identified project effects, and impacts and proposed mitigations and management approaches. #37 – COMMUNITY INFORMATION SESSION Date: October 17, 2024 Location: Virtual TCG Participation or Lead: Yes Presentation: Application Review Presentation Session Notes: TCG conducted a Tahltan-focused engagement virtually for all Tahltan Membership, where Skeena was invited to participate. The presentations provided information on the Project’s EAC Application, the identified project effects, and impacts and proposed mitigations and management approaches. --- PAGE 10 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 10 #39 – PUBLIC & TAHLTAN COMMUNITY INFORMATION SESSION Date: November 7, 2024 Location: Virtual TCG Participation or Lead: Yes Presentation: Skeena VIS Presentation.pdf Session Notes: Skeena participated in a virtual information session hosted by the TCG and BC EAO on November 7, 2024, as part of the initial EAC Application’s Application Review Public Comment Period. The EA process and Valued Component chapters of the initial EAC Application were presented. #40 – SHOEKAWK FAMILY MEETING Date: November 14, 2024 Location: Virtual TCG Participation or Lead: Yes Session Notes: The TCG Lands Director presented to the ShoeKawk Family on the Section 7 Consent Agreement explaining the Tahltan Assessment process, procedural process under the Agreement, and answered questions about the Project. #38 – PUBLIC & TAHLTAN COMMUNITY INFORMATION SESSION Date: November 5, 2024 Location: Virtual TCG Participation or Lead: Yes Presentation: Skeena VIS Presentation.pdf Session Notes: Skeena participated in a virtual information session hosted by the TCG and B.C. EAO on November 5, 2024, as part of the initial EAC Application’s Application Review Public Comment Period. The EA process and Valued Component chapters of the initial EAC Application were presented. #41 – TAHLTAN OPEN HOUSE Date: December 1, 2024 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Presented Tahltan Information Package and Project Effects Outcomes of Proponent Application Session Notes: The TCG held a full day open house with an evening presentation. TCG provided an Eskay Creek Revitalization Project Information Package to Tahltan membership, went over the project effects for Tahltan Values and informed membership on how they could provide feedback and questions on the information package for a 30 day period. Packages were also dropped off at the TCG and TNDC Office for membership to pick up. --- PAGE 11 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 11 #42 – TAHLTAN OPEN HOUSE Date: December 2, 2024 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Presented Tahltan Information Package and Project Effects Outcomes of Proponent Application Session Notes: The TCG held a second full day open house with an evening presentation. TCG provided an Eskay Creek Revitalization Project Information Package to Tahltan membership, went over the project effects for Tahltan Values and informed membership on how they could provide feedback and questions on the information package for a 30 day period. Packages were also dropped off at the TCG and TNDC Office for membership to pick up. #43 – TAHLTAN OPEN HOUSE Date: December 3, 2024 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: Presented Tahltan Information Package and Project Effects Outcomes of Proponent Application Session Notes: The TCG held a full day open house with an evening presentation. TCG provided an Eskay Creek Revitalization Project Information Package to Tahltan membership, went over the project effects for Tahltan Values and informed membership on how they could provide feedback and questions on the information package for a 30 day period. Packages were also dropped off at the Tahltan Band Office for membership to pick up. #44 – TAHLTAN OPEN HOUSE Date: December 4, 2024 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: Presented Tahltan Information Package and Project Effects Outcomes of Proponent Application Session Notes: The TCG held a second full day open house with an evening presentation. TCG provided an Eskay Creek Revitalization Project Information Package to Tahltan membership, went over the project effects for Tahltan Values and informed membership on how they could provide feedback and questions on the information package for a 30 day period. Packages were also dropped off at the Tahltan Band Office for membership to pick up. #45 – TAHLTAN OPEN HOUSE Date: December 5, 2024 Location: Iskut TCG Participation or Lead: Yes Presentation: Presented Tahltan Information Package and Project Effects Outcomes of Proponent Application Session Notes: The TCG held a full day open house with evening Presentation through a PowerPoint presentation. TCG provided an Eskay Creek Revitalization Project Information Package to Tahltan membership, went over the project effects for Tahltan Values and informed membership on how they could provide feedback and questions on the information package for a 30 day period. Packages were also dropped off at the Iskut Band Office and sent to the Red Chris Mine for Tahltan membership to pick up. --- PAGE 12 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 12 #46 – TAHLTAN OPEN HOUSE Date: December 6, 2024 Location: Iskut TCG Participation or Lead: Yes Presentation: Presented Tahltan Information Package and Project Effects Outcomes of Proponent Application Session Notes: The TCG held a second full day open house with evening Presentation through a PowerPoint presentation. TCG provided an Eskay Creek Revitalization Project Information Package to Tahltan membership, went over the project effects for Tahltan Values and informed membership on how they could provide feedback and questions on the information package for a 30 day period. Packages were also dropped off at the Iskut Band Office and sent to the Red Chris Mine for Tahltan membership to pick up. #47 – COMMUNITY INFORMATION SESSION Date: December 10, 2024 Location: Vancouver TCG Participation or Lead: No Presentation: No Session Notes: Skeena held a Tahltan Open House in Vancouver on December 10, 2024 at the Hyatt Hotel. Similar to the EA Application Review Public Comment Period information sessions, the Open House featured poster boards on EA Valued Component chapters. #48 – OPEN HOUSE Date: January 13, 2025 Location: Prince George TCG Participation or Lead: No Presentation: No Session Notes: Skeena hosted a Tahltan Open house to discuss the Eskay Creek Revitalization Project (ECRP) generally. No presentation was shared, instead it was an open dialogue format to discuss the ECRP. #49 – LEADERSHIP PRESENTATION Date: January 21, 2025 Location: Vancouver TCG Participation or Lead: Yes Presentation: TCG_Roundup_Presentation_Jan-2025.pdf Session Notes: Skeena attended a leadership meeting organized by TCG at Roundup, to present to Tahltan Leadership an update on the status of the project EAC Application Review Process. --- PAGE 13 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 13 #50 – COMMUNITY INFORMATION SESSION Date: March 10, 2025 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: 202503-V3-SKE-Tahltan Engagement Presentation.pptx Session Notes: TCG hosted an open-house with Skeena participation in Telegraph Creek. The purpose of the session was to provide an update on the Revised Application in-line with the issuance of the Application Notice direction and outcomes of the Application Review 180 day process. Additional feedback and information was provided to membership and input collected on proposed effects, mitigations and management approaches. #51 – TAHLTAN OPEN HOUSE Date: March 11, 2025 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: TCG Presentation on Outcomes of Joint Notice and Eskay Creek Information Package Update Session Notes: TCG hosted a second day of open house and presentation on Outcomes of the Joint Notice and provided an Eskay Creek Information Package Update for membership. TCG provided additional information on potential Tahltan conditions or strategies to reduce, avoid or accommodate for potential effects and discussed these with membership. A Tahltan membership information package was provided to Membership and made available the Tahltan Band Office. #52 – COMMUNITY INFORMATION SESSION Date: March 12, 2025 Location: Iskut TCG Participation or Lead: Yes Presentation: 202503-V3-SKE-Tahltan Engagement Presentation.pptx Session Notes: TCG hosted an open-house with Skeena participation in Iskut. The purpose of the session was to provide an update on the Revised Application in-line with the issuance of the Application Notice direction and outcomes of the Application Review 180 day process. Additional feedback and information was provided to membership and input collected on proposed effects, mitigations and management approaches. #53 – TAHLTAN OPEN HOUSE Date: March 13, 2025 Location: Iskut TCG Participation or Lead: Yes Session Notes: TCG hosted a second day of open house and presentation on Outcomes of Joint Notice and Eskay Creek Information Package Update for membership. TCG provided additional information on potential Tahltan conditions or strategies to reduce, avoid or accommodate for potential effects and discussed these with membership. A Tahltan membership information package was provided to Membership and made available at the Iskut Band Office. --- PAGE 14 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 14 #54 – COMMUNITY INFORMATION SESSION Date: March 14, 2025 Location: Dease Lake TCG Participation or Lead: Yes Presentation: 202503-V3-SKE-Tahltan Engagement Presentation.pptx Session Notes: TCG hosted an open-house with Skeena participation in Dease Lake. The purpose of the session was to provide an update on the Revised Application in line with the issuance of the Application Notice direction and outcomes of the Application Review 180 day process. Additional feedback and information was provided to membership and input collected on proposed effects, mitigations and management approaches. #55 – TAHLTAN OPEN HOUSE Date: March 15, 2025 Location: Dease Lake TCG Participation or Lead: Yes Session Notes: TCG hosted a second day of open house and presentation on Outcomes of Joint Notice and Eskay Creek Information Package Update for membership. TCG provided additional information on potential Tahltan conditions or strategies to reduce, avoid or accommodate for potential effects and discussed these with membership. A Tahltan membership information package was provided to Membership and made available at the TCG and TNDC Office. #56 – ETH’ENI FAMILY MEETING Date: March 18, 2025 Location: Virtual TCG Participation or Lead: Yes Presentation: Presented to the Eth’eni Family on the Eskay Creek Project EA Process, Effects, Mitigations and Tahltan Conditions Session Notes: The TCG Lands Director presented to the Eth’eni Family on the Eskay Creek Project EA Process, an overview of the Proposed Project, Potential Effects, Mitigations and strategies and potential Tahltan Conditions. #57 – TAHLTAN OPEN HOUSE Date: March 20, 2025 Location: Whitehorse TCG Participation or Lead: Yes Presentation: Membership Open House with Information Packages and Project Videos Session Notes: TCG and Skeena held an open house for Tahltan membership during the All Native Hockey Tournament in Whitehorse for 2 days. Materials about the project, representatives and information was distributed during a two day period. --- PAGE 15 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 15 #58 – TAHLTAN OPEN HOUSE Date: March 21, 2025 Location: Whitehorse TCG Participation or Lead: Yes Presentation: Membership Open House with Information Packages and Project Videos Session Notes: TCG and Skeena held an open house for Tahltan membership during the All Native Hockey Tournament in Whitehorse for 2 days. Materials about the project, representatives and information was distributed during a two day period. #59 – VIRTUAL WEBSITE LAUNCH Date: April 17, 2025 Location: Eskay Creek Website Launch TCG Participation or Lead: Yes Presentation: TCG Launched a external Tahltan membership only Website with Project Information for Membership on the Environmental Assessment and abilities to contact TCG Lands Department for feedback and input. Session Notes: TCG Launched an external Tahltan membership only Website with Project Information for Membership on the Environmental Assessment and abilities to contact TCG Lands Department for feedback and input. #60 – MEMBERSHIP EA UPDATE & IBA Date: April 22, 2025 Location: Vancouver & Virtual TCG Participation or Lead: Yes Presentation: Membership Updated Meeting with Leadership on Tahltan Assessment, Environmental Assessment, and IBA Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Tahltan Assessment, Environmental Assessment, provided a project overview and the status of the Impact Benefit Agreement negotiations to seek feedback and direction from membership. Vancouver was also offered as a virtual session for Tahltan membership. #61 – MEMBERSHIP EA UPDATE & IBA Date: April 23, 2025 Location: Whitehorse TCG Participation or Lead: Yes Presentation: Membership Updated Meeting with Leadership on Tahltan Assessment, Environmental Assessment, and IBA Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Tahltan Assessment, Environmental Assessment, provided a project overview and the status of the Impact Benefit Agreement negotiations to seek feedback and direction from membership. --- PAGE 16 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 16 #62 – MEMBERSHIP EA UPDATE & IBA Date: April 24, 2025 Location: Dawson Creek TCG Participation or Lead: Yes Presentation: Membership Updated Meeting with Leadership on Tahltan Assessment, Environmental Assessment, and IBA Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Tahltan Assessment, Environmental Assessment, provided a project overview and the status of the Impact Benefit Agreement negotiations to seek feedback and direction from membership. #63 – MEMBERSHIP EA UPDATE & IBA Date: April 25, 2025 Location: Kelowna TCG Participation or Lead: Yes Presentation: Membership Updated Meeting with Leadership on Tahltan Assessment, Environmental Assessment, and IBA Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Tahltan Assessment, Environmental Assessment, provided a project overview and the status of the Impact Benefit Agreement negotiations to seek feedback and direction from membership. #64 – MEMBERSHIP EA UPDATE & IBA Date: May 4, 2025 Location: Terrace TCG Participation or Lead: Yes Presentation: Membership Updated Meeting with Leadership on Tahltan Assessment, Environmental Assessment, and IBA Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Tahltan Assessment, Environmental Assessment, provided a project overview and the status of the Impact Benefit Agreement negotiations to seek feedback and direction from membership. #65 – MEMBERSHIP EA UPDATE & IBA Date: May 5, 2025 Location: Smithers TCG Participation or Lead: Yes Presentation: Membership Updated Meeting with Leadership on Tahltan Assessment, Environmental Assessment, and IBA Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Tahltan Assessment, Environmental Assessment, provided a project overview and the status of the Impact Benefit Agreement negotiations to seek feedback and direction from membership. --- PAGE 17 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 17 #66 – MEMBERSHIP EA UPDATE & IBA Date: May 6, 2025 Location: Prince George TCG Participation or Lead: Yes Presentation: Membership Updated Meeting with Leadership on Tahltan Assessment, Environmental Assessment, and IBA Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Tahltan Assessment, Environmental Assessment, provided a project overview and the status of the Impact Benefit Agreement negotiations to seek feedback and direction from membership. #67 – COMMUNITY INFORMATION SESSION Date: May 26, 2025 Location: Iskut TCG Participation or Lead: Yes Presentation: 202505-SKE-Tahltan Territory Technical Water Engagement-DL Pres.pdf Session Notes: Skeena and TCG held a community engagement with Tahltan membership to discuss the Tailings Facility Water Treatment Plant and other aspects of water management risk, mitigations and potential management approaches for the Project. #68 – COMMUNITY INFORMATION SESSION Date: May 27, 2025 Location: Dease Lake TCG Participation or Lead: Yes Presentation: 202505-SKE-Tahltan Territory Technical Water Engagement-DL Pres.pdf Session Notes: Skeena and TCG held a community engagement with Tahltan membership to discuss the Tailings Facility Water Treatment Plant and other aspects of water management risk, mitigations and potential management approaches for the Project. #69 – COMMUNITY INFORMATION SESSION Date: May 28, 2025 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: 202505-SKE-Tahltan Territory Technical Water Engagement-DL Pres.pdf Session Notes: Skeena and TCG held a community engagement with Tahltan membership to discuss the Tailings Facility Water Treatment Plant and other aspects of water management risk, mitigations and potential management approaches for the Project. --- PAGE 18 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 18 #70 – ELDERS COUNCIL PRESENTATION Date: July 3, 2025 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Presentation to Elders on the Eskay Creek Project, Effects, Mitigations, Conditions and Tahltan Assessment Session Notes: TCG Lands Department presentation to the Tahltan Elders Council on the Tahltan Assessment for the Eskay Creek Project. Discussions included an overview of the project, videos, overview of project effects, proposed mitigations, and potential Tahltan Conditions. #71 – AGA MEMBERSHIP PRESENTATION Date: July 4, 2025 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Presentation to Membership on the Eskay Creek Project, Effects, Mitigations, Conditions and Tahltan Assessment Session Notes: TCG Lands Department presentation to the Tahltan membership at the 2025 AGA on the Tahltan Assessment for the Eskay Creek Project. Discussions included an overview of project effects, proposed mitigations, and potential Tahltan Conditions, and the Section 7 Tahltan decision-making process. #72 – TCG LANDS DEPARTMENT BOOTH Date: July 4, 2025 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Handed out Eskay Creek Project Materials, Information Packages, Tahltan Risk Assessment Materials, Videos of Project Session Notes: The TCG Lands Department hosted a Department Booth during the 2025 AGA for Tahltan membership to pick up information packages on the Eskay Creek Project, watch a project overview video and groundwater modelling video. In addition, answer questions about the project and discuss project potential effects, proposed mitigations and potential Tahltan conditions. #73 – TCG LANDS DEPARTMENT BOOTH Date: July 5, 2025 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Handed out Eskay Creek Project Materials, Information Packages, Tahltan Risk Assessment Materials, Videos of Project Session Notes: The TCG Lands Department hosted a Department Booth during the 2025 AGA for Tahltan membership to pick up information packages on the Eskay Creek Project, watch a project overview video and groundwater modelling video. In addition, answer questions about the project and discuss project potential effects, proposed mitigations and potential Tahltan conditions. --- PAGE 19 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 19 #74 – TCG LANDS DEPARTMENT BOOTH Date: July 6, 2025 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Handed out Eskay Creek Project Materials, Information Packages, Tahltan Risk Assessment Materials, Videos of Project Session Notes: The TCG Lands Department hosted a Department Booth during the 2025 AGA for Tahltan membership to pick up information packages on the Eskay Creek Project, watch a project overview video and groundwater modelling video. In addition, answer questions about the project and discuss project potential effects, proposed mitigations and potential Tahltan conditions. #75 – MEMBERSHIP IBA UPDATE & ENV Date: September 13, 2025 Location: Telegraph Creek TCG Participation or Lead: Yes Presentation: Eskay Creek IBA and ENV Tour Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Eskay Creek Impact Benefit Agreement Negotiations. This included: financials, business opportunities, education and training, community wellness, environmental commitments, and other topics. #76 – MEMBERSHIP IBA UPDATE & ENV Date: September 14, 2025 Location: Iskut TCG Participation or Lead: Yes Presentation: Eskay Creek IBA and ENV Tour Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Eskay Creek Impact Benefit Agreement Negotiations. This included: financials, business opportunities, education and training, community wellness, environmental commitments, and other topics. #77 – MEMBERSHIP IBA UPDATE & ENV Date: September 14, 2025 Location: Dease Lake TCG Participation or Lead: Yes Presentation: Eskay Creek IBA and ENV Tour Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Eskay Creek Impact Benefit Agreement Negotiations. This included: financials, business opportunities, education and training, community wellness, environmental commitments, and other topics. --- PAGE 20 --- Engagement Sessions for Eskay Creek Revitalization Project and/or IBA 20 #80 – MEMBERSHIP IBA UPDATE & ENV Date: September 17, 2025 Location: Prince George TCG Participation or Lead: Yes Presentation: Eskay Creek IBA and ENV Tour Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Eskay Creek Impact Benefit Agreement Negotiations. This included: financials, business opportunities, education and training, community wellness, environmental commitments, and other topics. #79 – MEMBERSHIP IBA UPDATE & ENV Date: September 16, 2025 Location: Smithers & Virtual TCG Participation or Lead: Yes Presentation: Eskay Creek IBA and ENV Tour Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Eskay Creek Impact Benefit Agreement Negotiations. This included: financials, business opportunities, education and training, community wellness, environmental commitments, and other topics. #78 – MEMBERSHIP IBA UPDATE & ENV Date: September 15, 2025 Location: Terrace TCG Participation or Lead: Yes Presentation: Eskay Creek IBA and ENV Tour Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Eskay Creek Impact Benefit Agreement Negotiations. This included: financials, business opportunities, education and training, community wellness, environmental commitments, and other topics. #81 – MEMBERSHIP IBA UPDATE & ENV Date: September 18, 2025 Location: Whitehorse TCG Participation or Lead: Yes Presentation: Eskay Creek IBA and ENV Tour Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Eskay Creek Impact Benefit Agreement Negotiations. This included: financials, business opportunities, education and training, community wellness, environmental commitments, and other topics. --- PAGE 21 --- LEARN MORE ESKAYIBA.TAHLTAN.ORG 21 Engagement Sessions for Eskay Creek Revitalization Project and/or IBA #82 – MEMBERSHIP IBA UPDATE & ENV Date: September 19, 2025 Location: Vancouver & Virtual TCG Participation or Lead: Yes Presentation: Eskay Creek IBA and ENV Tour Session Notes: TCG and Skeena presented to Tahltan membership on the status of the Eskay Creek Impact Benefit Agreement Negotiations. This included: financials, business opportunities, education and training, community wellness, environmental commitments, and other topics.